Latest Photos of Phước An Bridge 2026

Project

As of March 2026, the mega-project Phước An Bridge connecting Ho Chi Minh City and Đong Nai Province is witnessing rapid, continuous progress. Through non-stop day-and-night efforts, the contractor consortium of Trungnam E&C – Trung Chính has completed 8 stay cables at pier T38 and 7 stay cables at pier T37, progressing 7 months ahead of schedule and bringing the project into its crucial final phase toward main span closure.

Over 81% Work Volume Completed in March, 7 Months Ahead of Schedule

Phước An Bridge Project is undergoing its peak construction period. According to the latest work output report up to mid-March 2026:

  • Total Output Executed by Consortium: Reached VND 1,284.4 billion.

  • Overall Package Completion Rate: Reached 81.31%.

  • Construction Progress: Officially 7 months ahead of schedule compared to the contractual timeline.

Achieving a 7-month ahead-of-schedule milestone on a mega-project featuring highly complex technical structures is a rare record. It affirms the project management capabilities, equipment resources, and advanced technical execution standards of Vietnamese contractors.

hinh anh cau phuoc-an-moi-nhat
Latest photos of Phước An Bridge in March 2026, connecting Phu My (HCMC) with Đong Nai

8 Stay Cables Tensioned, Moving Toward Main Span Closure

Core technical items at main tower piers T37 and T38 are being deployed synchronously and with absolute precision:

  • Cable-Stayed System: To date, contractors have successfully installed and tensioned 8 stay cable strands at main tower pier T38. Engineers and workers of Trungnam E&C are urgently preparing to install stay cable No. 9 (S9) in the coming days.

  • Main Span Construction: Balanced cantilever segment casting is operating at maximum capacity using advanced formtraveler systems. Construction fronts from both main towers are rapidly approaching each other.

  • Auxiliary & Finishing Items: Parallel to main span development, contractors are expediting the construction of KT stub girders, preparing technical methodologies for main span closure, and finishing the parapet wall structures

hinh anh cau phuoc an-moi-nhat
Pier T38 where general contractor Trungnam E&C has completed stay cable No. 8

Phước An Bridge: Economic Connector for the Southeast Region

Phước An Bridge (commenced in June 2023) has a total investment of nearly VND 4,900 billion, a total length of 4.38 km, and a scale of 6 lanes. The highlight of the project is its main span utilizing an extradosed cable-stayed bridge structure with a length of 250 m and a navigation clearance height of 55 m, ensuring safe passage for vessels with capacities up to 30,000 DWT on the Thị Vải River.

Upon completion, Phước An Bridge will play a strategic role:

  • Directly connecting the Cái Mép – Thị Vải port complex with the Bến Lức – Long Thành Expressway and the HCMC – Long Thành – Dầu Giây Expressway.

  • Shortening freight transportation routes by nearly 30 km from the Mekong Delta region and HCMC to deep-water ports, helping reduce logistics costs by 20–30%.

  • Relieving severe traffic congestion on the existing National Highway 51.

With current breakthrough construction progress, the seamless coordination of the Trungnam E&C – Trung Chính contractor consortium is turning the vision of opening the bridge to traffic ahead of schedule into reality, making a significant contribution to infrastructure and economic development across Bà Rịa – Vũng Tàu, HCMC, Đồng Nai, and the Southern Key Economic Zone.