INSTALLATION OF HIGH-SPEED HIGHWAY LIGHTING SYSTEM KHANH HOA – BUON MA THUOT

Project

The latest progress on Khanh Hoa – Buon Ma Thuot highway has reached nearly 80% construction output, with Trungnam E&C concentrating all efforts to complete the asphalt surface layer and install the lighting system at the Provincial Road 10 bridge section.

Accelerating Towards 80% Progress at Package 03

In early December, the labor atmosphere at the high-speed highway construction site managed by Trungnam E&C is extremely urgent. Taking advantage of favorable weather conditions in November and December, all construction teams have operated at full capacity to accelerate progress.

The appearance of the highway section (from km 101+500 to km 117+593) spanning over 16km is gradually becoming complete, marking an important transition from the foundation construction phase to the finishing phase.

Khanh Hoa - Buon Ma Thuot expressway
The C16 polymer asphalt concrete pavement layer on the route is part of the Dak Lak component

Completing the Road Surface and Organizing Traffic

To ensure quality and aesthetic appeal for the project when put into operation, engineers and workers are focusing intensely on the final technical components:

• Polymer C16 Asphalt Concrete Layer: This is the key item determining the smoothness and durability of the highway. Construction work is closely supervised to ensure strict compliance with technical requirements for temperature and compaction standards.

• Traffic Safety System: In parallel with surfacing, numerous directional signs and guardrail systems are being installed comprehensively. These components not only create a “safe corridor” but also contribute to professional appearance for the entire contract package.

Highlight at the Intersection (TL10) One of the notable components during November construction was the completion of the lighting system at this intersection area. Light poles and the electrical lighting system on the bridge are being rapidly installed and connected. When completed, this lighting system will ensure maximum visibility and safety for vehicles passing through the bridge area, while creating a modern landscape highlight for the project at night.

Cao toc-Khanh-hoa-Buon-ma-thuot
Workers are installing railings, lighting systems, and other auxiliary items

Bringing Experience to Every Project

Trungnam E&C is a company with many years of experience in traffic infrastructure construction, notably executing projects in parallel such as the Bien Hoa – Vung Tau Highway and Chau Doc – Can Tho – Soc Trang Highway. We remain committed to maintaining the current acceleration pace. The entire team of Trungnam E&C staff continues to stay close to the construction site, committed to ensuring schedule and quality at the highest level, ready to bring the project to completion on schedule, meeting the expectations of investors and local communities in the project area.