As of July 2026 Progress of Provincial Road 8 Overpass Project: Achieved over 24% of total construction output.
-
Completed bored piling for Pier T04 and continuing construction on Pier T05, establishing a solid foundation for subsequent construction phases.
-
Constructing the footing, stem, and pier cap for Pier T04. Setting up the girder fabrication yard and installing the gantry crane system for span structure erection.
-
Parallel roads 3 and 4, along with temporary traffic detour routes: Reached approximately 50% completion, progressively perfecting the project’s synchronized infrastructure.