Project progress update: Ring Road II – Hanoi.

Company news

Immediately after the groundbreaking ceremony, the Contractor started construction with many construction teams at the same time.

After 4 months of construction, up to now (end of July 2018), 168/302 D1500 bored piles, 11/38 main bridge piers have been constructed,

The goal of Trung Nam EC and Trung Chinh is to complete package 3 (from pier P63 to pier P100) within 14 months, bringing the greatest benefit to the investor, saving costs and ensuring project construction progress.